JSWENERGY / guidance tracker

Keep management guidance in view.

JSW Energy · forward-looking guidance across the available source record.

Research layer active

Guidance tracker

What management said would happen.

FY27 Capacity Addition Target: 3 GW

Already achieved 36% of annual target (1.1 GW since April) and surpassed 87% of total FY26 additions. July YTD additions of 225 MW reinforce H1 momentum.

expansion

FY27 Capex Target: ₹20,000 Crore

Substantial liquidity cushion of ₹12,880 crore in cash balances comfortably funds equity portion of FY27 capex and 2030 growth plans.

capex

Mahanadi Unit 4 (600 MW) Commissioning: FY28

Fourth unit of Mahanadi on track for FY28 commissioning. 30-40% work already complete at acquisition. Equipment orders placed with Chinese suppliers. Material under dispatch.

expansion

BESS Business EBITDA Run-rate: ₹150 Crore

External order of ₹440 crore received. Margin per kWh of storage capacity in range of $2.75-3.00, translating to ~$15 million annual EBITDA (~₹150 crore) at full capacity utilization.

revenue

Hydro Plants Expected to Catch Up Full-Year Design Energy

With monsoon onset, water flows normalized. Kachham, Baspa, and Khar plants operating at >100% PLF in July. Design energy achievement expected for full year despite Q1 shortfall.

growth

Capacity target: 15+ GW by FY26 end

Company is well-positioned to achieve generation capacity target in excess of 15 GW by end of fiscal year, driven by 2.3 GW already added in H1 and accelerated execution pace expected in H2.

expansion

Utkal 400 MW LOA conversion expected

LOA of 400 MW for 700 MW plant expected to convert to PPA, which will reduce merchant exposure from current 8% to 5% and enhance cash flow predictability.

revenue

Vijagar 3,800 MWh BESS commissioning imminent

Commissioning of the 3,800 MWh battery energy storage project at Vijagar expected very soon in Q3 FY26.

expansion

Battery assembly plant operational Q3 FY26

5 GWh/year battery assembly plant in Pune dedicated to BESS expected to be operational in Q3 FY26, serving captive needs and potentially external demand.

expansion

H2 FY26 Capacity Addition Target of 1.5 GW On Track

125 MW commissioned in Q3; remaining capacity additions in Q4 are at advanced stage with grid connectivity and land secured for all projects.

expansion

Utkal 400 MW PPA Commencing April 2026

25-year PPA with Karnataka discom at ₹5.78/kWh (fixed) will reduce merchant exposure from 8% to ~5% from April 1, 2026.

revenue

Saloni Phase 1 (1.6 GW) Commissioning Within PPA Timelines

48 months from notice to proceed for first unit, 54 months for second unit; BTG orders placed with Toshiba GSW; total project investment ~₹16,000 crore.

expansion

KSK Additional 1.8 GW Commissioning in ~3 Years

Fourth unit (30-40% complete at acquisition) to commission first, followed by remaining two units at 3-6 month intervals; lower specific capex vs greenfield.

expansion

FY27 capacity addition of ~3 GW

Management expects to commission approximately 3 GW of renewable capacity in FY27, split roughly 35-40% wind and rest solar, with half in H1.

growth

FY27 capex of ~₹20,000 crore

Capital expenditure for FY27 is guided at around ₹20,000 crore, funded through internal cash flows and existing debt headroom.

capex

KSK Mahanadi first 600 MW unit commissioning by Q3 FY27

The first 600 MW unit of the remaining KSK Mahanadi capacity is expected to be commissioned by Q3 of next fiscal.

growth

2030 net debt to EBITDA target of ~5-5.5x

Management reiterated a net debt to EBITDA target of approximately 5 to 5.5 times by 2030, with deleveraging expected as cash flows improve.

other