JKLAKSHMI / bear-case history

Track the concerns that keep returning.

JK Lakshmi Cement · risk themes across the available quarters.

Research layer active

Bear-case history

Risks carried through the record.

Fuel Cost Inflation in Q2

Fuel cost expected to rise from Rs 1.65 to Rs 1.80-1.85 per unit in Q2, coinciding with monsoon-driven demand weakness. Management acknowledged this will 'hit margins' but expects industry-wide pass-through to occur. Packaging costs also up Rs 3.5-4 per bag (from Rs 134 to Rs 145), adding ~Rs 80/tonne.

high

Assam Land Litigation for Northeast Expansion

Villagers near the Garbhali plant site (Mahabal Cement subsidiary) filed a PIL in Gauhati High Court claiming land ownership. JK Lakshmi was added as respondent since Mahabal is a subsidiary. Management characterized this as routine land acquisition disputes but noted it adds regulatory uncertainty to the Northeast timeline.

medium

Geopolitical Supply Chain Disruption

Middle East conflict has disrupted imported coal and petcoke supply chains, disproportionately impacting northern plants that relied more on imports. Petcoke mix increased to 40% (from 14% YoY) as substitute, but imported coal at $130-135 remains elevated. Diesel price inflation partially offset by lead distance reduction.

medium

Proxy Advisor Governance Concerns

International proxy advisors recommended negative votes on AGM resolutions despite full legal compliance. While all resolutions passed with mutual fund support, institutional investors with foreign linkages followed proxy advisor recommendations. Management expressed frustration at inability to engage proactively before recommendations were published.

low

Sharp realization decline may persist

Realizations fell ~9% QoQ due to non-trade price weakness and higher Gujarat mix; recovery is uncertain given competitive pressures.

high

Trade price recovery may be delayed

Management expects trade prices to rise, but analysts questioned the timing; management admitted volatility and declined to quantify.

medium

Capex execution risk

The ₹3,000cr expansion has a tight timeline; any delay in equipment installation or land acquisition could push commissioning beyond Mar'28.

medium

Conveyor belt project stalled

The conveyor belt project is stalled due to land issues, with ₹170cr balance capex uncertain; this could impact logistics cost savings.

low