Material risks this quarter

Delay in capacity commissioning

Six projects delayed by a quarter due to torrential rains and floods, posing risk to timely capacity additions.

medium

Working capital increase

Working capital increased by ~₹2,000 crore in H1 due to higher receivables and inventory, which could pressure cash flows if not managed.

medium

Lower capacity utilization of acquired assets

Overall capacity utilization at 65-67%, with acquired assets like Sanghi underperforming; improvement needed to achieve operating leverage.

medium

Fuel cost volatility

While coal costs are currently low, any reversal could impact the cost reduction trajectory and margin expansion.

low